Facility Directory Table List

Print
Press Enter to show all options, press Tab go to next option

Project Description:

155th Street (also known as Arnold Avenue) is located on the southern Kansas City city-limits line and borders the City of Belton, Missouri. The one-mile long project begins near Scott Avenue just west of I-49 and runs west ending at the intersection with Kensington Avenue.

Roadway improvements include:

  • Widening the 2-lane roadway to 4-lanes with a median island
  • Sidewalk on the north side
  • Multi-use trail on the south side
  • A new storm sewer system
  • New street lighting

Traffic Impact:

The road will remain open during construction.

Project Timeline: 

Current status:   June 2019 - Complete storm sewer and major grading

General project timeline:  Construction began in February 2019 and is expected to be complete by December 2019 (weather permitting).

Project Contacts:

Anthony Sands, Project Manager

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2617

Maggie Green, Public Information Officer

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2612

GOKC Logo

Project Number:

89008156

Return to full list >>