    Project Update: 

    Update, April 26, 2021: 

    Work will begin on May 3, 2021 to continue the on-street cycle track north from Linwood to McGee Trafficway. We anticipate the project to take two weeks, weather permitting. 

    View the project plans for this section. 

    Project Description: 

    This project will install Complete Streets improvements--improved pedestrian crossings and a two-way cycletrack-- on Gillham Plaza from Armour Boulevard to McGee Trafficway. The goals of this project align with KCMO's Complete Street ordinance to make our streets safer and more accessible for all users: bicyclists, pedestrians, transit-users, and vehicles. 

    gillham drone photo

    Project improvements include: 

      IMG_5139
  • Traffic calming and improved pedestrian crossings on cross streets
  • An on-street, two-way cycle track from Armour toMcGee Trafficway
  • Improved, northbound bus stops at Linwood and at Armour
  • Upgraded traffic signal at Linwood Blvd and Gillham Plaza
  • Newly resurfaced roadway
  • Minimal impact to parking, trees, and existing traffic lanes
  • IMG_5137

    What is a two-way cycle track?

    Read more about a two-way cycle track design in the NACTO Urban Bikeway Design Guide.

     gillham drone photo 2

     

     

    Project Background: 

    • Previous public engagement process took place through the 2017 Gillham Road Planning Sustainable Places Study
    • Recommendations from this plan informed the final project design
    • The KCMO staff mobility committee met monthly in 2019 to refine the conceptual design and come up with an implementable project
    • Project funding is provided by the Complete Streets set-aside in the 2019-2020 Street Preservation Budget 

    Traffic Impact: 

    There is no work occurring at this time. Once construction starts later this spring/early summer, traffic will still be able to travel on Gillham, but the active construction and equipment will result in reduced travel lanes and possibly delays. 

    Transit Impacts: 

    • This project will remove three bus stops:
      • Two northbound stops: at Gillham Plaza and at Gillham Rd/34th
      • One southbound stop: at Gillham Rd/34th
    • The northbound bus stops at Armour and Linwood will be preserved and improved. 

    Project Timeline: 

    The northern section of the facility from Linwood to McGee Trafficway will be installed in late spring/early summer 2021, along with traffic signal upgrades. This will complete the work for this phase (Armour Boulevard to McGee Trafficway). 

    Project Contacts: 

    Randy Alewine, Project Manager

    Public Works Department— KCMO

    Phone: (816) 513-2589

    Public Works Department, General Inquiries

    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746