Project Description:

This project was completed in May, 2019. Beacon Hill is located just east of Crown Center. Infrastructure improvements for the Beacon Hill area include roadway improvements of Forest Avenue between 25th and 27th Street, and 26th Street from approximately 80' east of Troost to Tracy Avenue.

Roadway improvements include:

  • Street pavement
  • Concrete alleys
  • Curb & gutter
  • Streetlight replacement
  • Sidewalk
  • Water line
  • Sanitary sewer
  • Landscaping
  • Storm sewer improvements

Project Timeline:        

Current status:  April 2018 - May 2019: Construction complete

General project timeline:  Construction is completing as minor construction items are wrapping up. It is expected to be complete summer 2019.

Project Contacts:

Kim Pemberton, Project Manager

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2741

Maggie Green, Public Information Officer

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2612

GOKC Logo

Project Number:

89008263