    Project Description:

    Byrams Ford Road is located south of Kaufman Stadium.  The project will focus on re-opening the closed bridge.

    Roadway improvements include:

    • New replacement bridge
    • New sidewalk on bridge

    View Byrams Ford Road Bridge Reopening Project on the map

    Traffic Impact:

    This project is currently in the design phase, there are no impacts to traffic at this time.

    Project Timeline:        

    January 2026 update: Final design complete and the RER (environmental permitting) process is finalized.

    General project timeline:  This project is currently in the design phase and the project team has started the acquisition process. Notice letters have gone out to residents. Project going out to bid in mid-2026.

    The Missouri Department of Transportation’s (MODOT) Region Bridge Program and the Mid-America Regional Council (MARC) awarded $1,237,500 in funding to repair the bridge. The Public Works project will require a 20% funding match of $412,500 dollars.

    Project Contacts:

    Aaron Peck Project Manager, Public Works

    Phone: 816-513-2572

    Public Works Department, General Inquiries

     

     GOKC Logo

    Project Number:

    89005582
    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746

    • Capital Projects Fountain

      Kansas City identifies potential connector streets in a "Major Street Plan" that is updated every few years