Capital Projects

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

    Project Description:

    The Gregory Boulevard Bridge is located over the Blue River just south of the Kansas City Zoo. The bridge currently has one of the highest volume traffic bridges with the worst structural rating.

    Roadway improvements include:

    • Funding has been allocated for full replacement project, rather than rehab an over 100 year old bridge
    • Pedestrian and bicycle facilities will be incorporated in new bridge design with bike lanes, and 8' shared use path on north side of bridge

    View Gregory Boulevard Bridge Repairs Project on the map

    Traffic Impact:

    This project is currently in the design phase, there are no impacts to traffic at this time.

    Project Timeline:        

    July 2022: 60% Plans completed, railroad and utility coordination underway 

    General project timeline:  This project is currently in the design phase and a construction funding available in 2020.

    Project Contacts:

    Kim Pemberton, Project Manager

    Public Works Department— KCMO

    Phone: (816) 513-2741

     GOKC Logo

    Project Number:

    89008587
    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746

    • Capital Projects Fountain

      Kansas City identifies potential connector streets in a "Major Street Plan" that is updated every few years