Project Description:

North Oak Trafficway runs parallel to MO Route 169.  Roadway reconstruction of North Oak Trafficway spans from the North Kansas City City Limits to North Indianola Drive.

Roadway improvements include:

  • Replacement of existing pavement
  • New curb and gutter
  • New sidewalks on both sides along north portion of project boundaries
  • Shared use facility on south portion connecting to North Kansas City bike facilities
  • Six bus stop sidewalk pad installations
  • New and enlarged water lines
  • New street lights
  • Slope improvements south of Cerner

Project Plans:

You can view the project plans for this reconstruction here: North Oak Plans

Project Timeline:        

Current status: Final punch list items are being completed. Ribbon Cutting event took place on November 13, 2019. 

General project timeline:  Construction started fall 2018 and completion is expected in fall 2019.

Public Engagement:

City leaders and project representatives celebrated the completion of roadway improvements on N. Oak Trafficway from the NKC City Limits to N. Indianola Avenue on November 13, 2019.

N. Oak Ribbon Cutting

Project Contacts:

David Miller, Project Manager

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2746

Maggie Green, Public Information Officer

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2612

 GOKC Logo

Project Number:

89008573

Return to full list >>