    Project Overview

    Involves the replacement of a closed bridge on Raytown Road between Highway 150 and 137th Street. This project is currently in the construction phase, and there are no impacts to traffic at this time as the existing structure is closed.

    There will be a ribbon cutting ceremony on Monday, August 10, 2026 at 3:30 PM, and the bridge will reopen at the conclusion of the ceremony.

    a photo of the restored bridge on Raytown Road over the Lumpkins Fork stream

    Project Timeline

    Bids opened in Summer 2025, with the contract being awarded in Fall 2025. Major construction is underway as of March 2026, with completion expected in Summer 2026.

    Project Contacts:

    Aaron Peck, Project Manager

    Public Works Department— City of Kansas City, MO

    Phone: (816)-513-2572

    Public Works Department, General Inquiries

    Project Number: 89005596

    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746

    • Capital Projects Fountain

      Kansas City identifies potential connector streets in a "Major Street Plan" that is updated every few years