    Update 10/1/2025: 

    Construction continues, with work on the north side of Stadium Drive at 90% completion. South side construction has started from the Bridge to the Railroad tracks.

    Project Overview 

    This streetscape project spans along Stadium Drive from Raytown Road to East 31st Street. The streetscape includes the following improvements:

    • Lane reconfiguration/road diet: converting lanes to two through lanes and a continuous center turn lane
    • New sidewalks
    • Addition of a raised shared use path/trail on the south side of Stadium Drive
    • Shared through lanes

    Construction is happening in phases:

    • Phase 1 – North Side E 31st to Raytown Rd – 90% completed
    • Phase 2 – South Side E 31st to E 34th Ter & E 35th Ter to Raytown Rd – Under construction
    • Phase 3 – E 34th Ter to E 35th Ter (Park)

    Traffic Impact

    Traffic is reduced to one lane each direction during construction, which will also be the case permanently once the construction is completed.

    Timeline

    • Construction started in July 2025
    • Construction expected to be complete by May 2026
    • Landscaping will be completed once construction is completed

    Contact Information

    Mia Puthumana - Project Manager

    Kansas City Public Works

    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746

    • Capital Projects Fountain

      Kansas City identifies potential connector streets in a "Major Street Plan" that is updated every few years