    The four way stop at 43rd and Pitman is located south of I-70 and east of Arrowhead stadium. The design will improve the roadway, replace the bridge, and make geometric improvements to the four-way stop.

    Roadway improvements include:

    • Road widening
    • Sidewalks on both sides
    • Curb and gutter
    • Streetlights
    • New bridge

    View 43rd and Pitman Roadway Improvements Project on the map

    Traffic Impact:

    This project is currently in the design phase, there are no impacts to traffic at this time.

    Project Timeline:        

    Current status: June 2022: 60% Design is complete and project is being put on hold until construction funding is available.

    General project timeline:  Design process began April 2019 and is currently ongoing. Construction fund is not available at this time.

    Project Contacts:

    Kim Pemberton, Project Manager

    Public Works Department– Kansas City, Mo.

    Phone: (816) 513-2741

    Project Number:

    89008242

    Return to full list >>

     

    Capital Projects can be filtered by project name, department, and address.

    Project Contacts

    District 1 & District 2 
    Todd LaTorella
    Assistant City Engineer, District Engineer
    (816) 513-0803

    District 3 & District 5
    Amy Bunnell
    District Engineer
    (816) 513-2748

    District 4 & District 6
    Randy Alewine
    District Engineer
    (816) 513-2589

    City Engineer
    Nicolas Bosonetto
    (816) 513-2746

    • Capital Projects Fountain

      Kansas City identifies potential connector streets in a "Major Street Plan" that is updated every few years