The Capital Projects Division manages key construction projects for the City of Kansas City, Mo. Public Works Department. Capital Projects staff are at the forefront of Kansas City’s construction renaissance, bringing process improvements and standardized practices to the management of street, bridge and building projects throughout the City. Personnel include project managers; construction inspectors; right-of-way, relocation and utility specialists; and finance and administrative professionals.

View the Major Streets Plan 

Contact Capital Projects

414 E. 12th Street, 18th floor
Kansas City, MO 64104
Phone: (816) 513-2739
Fax: (816) 513-2523

Projects Map

PROJECT UPDATE: (updated 12/23/19)

Contractor crews laid the final layer of asphalt over the weekend. Temporary striping was installed on Monday morning (12/23) and NW Prairie View Road was opened to traffic on Monday, December 23, 2019. 

Final items like sodding, landscaping, and permanent pavement markings will likely wait until spring when we have consistent, warmer weather. 

Project Description:

NW Prairie View Road is located just off of I-29 and Northwest 64th Street. This project will include the complete relocation of the outer road (NW Prairie View Road) on north side of NW 64th Street and realigning with existing N. Chatham Avenue.

Roadway improvements include:

  • Curb and gutter
  • Asphalt pavement
  • Realignment of driveways/private drives
  • Concrete sidewalk
  • Bike lanes
  • Storm sewer
  • Water main relocation
  • Street lighting and sod

View the final concept plan. This graphic shows what the area will look like when both Northern and Southern portions are completed. 

Traffic Impact:

The roadway was opened to traffic on December 23, 2019. 

Project Timeline:        

Current status:  The roadway was opened to traffic on December 23, 2019. Permanent striping, as well as final sodding/landscaping work will likely wait until spring-- this is all weather dependent. 

General project timeline:  Construction began August 2018 and is expected to be completed in early December 2019. 

Project Contacts:

Kim Pemberton, Project Manager

Public Works Department— KCMO

Phone: (816) 513-2741

Maggie Green, Public Information Officer

Public Works Department– Kansas City, Mo.

Phone: (816) 513-2612

 

Project Number:

89008174

Return to full list >>